全國服務熱線
13503801616
新聞資訊
News
YD多速電機如何接線
YD多速電機如何接線。、電動機Y/Y2/Y3/YE3系列電動機的繞組引出線為6根。YD/YZD/YDT系列雙速、三速及四速電動機根據不同繞組有可能為6/9/12根。
1. There are 6 lead-out wires of the motor windings for Y/Y2/Y3/YE3 series. The number of the lead-out
wires for the motor windings could be 6/9/12 depending on different windings types, for YD/YZD/YDT series
two-speed, three-speed and four-speed motors.
2、電動機的旋轉方向從軸伸端視為順時針方向,任意對調三相電源線中的兩根,電動機可改變轉向。
2. The rotation direction of the motor is clockwise (viewed from shaft extension end). Any swap between
two of the three-phase power lines can change the motor steering.
3、按照接線圖接好電源線(YD/YZD/YDT系列電動機要按照接線圖要求連接好引出線)。外接額定電壓進行電動機空載試驗。
注意:大極比S3(周期)工作制電動機空載試驗時間不宜過長,觀察電動機是否有異?,F象,否則應迅速斷電檢查。
3. Connect the power lines in accordance with the wiring diagram(the lead-out wires of the YD / YZD / YDT
series motor should be connected in accordance with its wiring diagramm). Power the motor with rating
voltage the test it with no-load at first.
Note: For motors with S3 operating system, the no-load test should not last too long. Observing are there any abnormal phenomenas, otherwise you should cut off the power supply immediately and check the system.
返回頂部